According to a report earlier this month from Ontario's auditor general Shelley Spence on the Ontario Place redevelopment, "the new building is expected to open…
Infrastructure Ontario's estimate for public realm work—exclusive of site servicing, shoreline repair, soil remediation, and roads—has increased tenfold from…
Planning continues for the relocation of Ontario Science Centre to Ontario Place, and we may expect to see continued environmental destruction at Ontario Place…
It’s still full speed ahead for the Ontario Place redevelopment and for Therme’s waterpark. Expect an early handover, the commercialization of public spaces,…
Information from the Auditor General's report points to the construction of a large 4-storey parkade at Exhibition Place to fulfill lease obligations to Ontario…
This article is part of a multi-part series examining findings from the Auditor General’s 2024 Report. Future parts will be posted in the coming week.
On…
On July 10, 2024, the Ontario government agreed to halt demolition pending the results of Ontario Place Protectors (OPP)'s challenge to the Rebuilding Ontario…
The $50-$100 M it will cost to demolish and set up a temporary location for the Science Centre would more than cover the $30 M needed in repairs for the next…
Two figures have been cited by the Ontario Government: $478 million and $369 million. The actual number is much less—around $200 million, or just $24 million…
The correspondence highlights that this timeline is deemed "excessively optimistic" considering the track record of past delays in real estate projects within…
The federal government intends to resurrect a post-war effort to ramp up housing construction across Canada, but with a 21st-century twist.
A consultation…
Kehm told the Toronto Star he could no longer be affiliated with a project that threatened the wildlife habitat, due to his professional commitment to…